The bathroom renovation process, step by step.
Knowing the order of work makes a renovation far less stressful. Here is how a bathroom renovation runs in Melbourne, from the first consultation to the final handover, and what happens at each stage.
Plan and choose first, then strip out, rough in, waterproof, tile and fit off. A bathroom renovation can take anywhere from 2 to 3 weeks, depending on how big the renovation is, with the planning done before the first tool is picked up.
Ten stages, in the order they happen.
-
1
Consultation and site assessment
Everything starts with a visit. We look at the existing room, measure up, check how the floor and walls are built and talk through how you use the space and what you want from it. This is where your scope and timeframe are first discussed, and it is also the time to mention any problems you already know about, such as leaks, damp or a floor that is not level.
-
2
Design, layout and selections
Next comes the plan: where the shower, vanity, toilet and bath go, what tile covers which surface, and which tapware, mirror and lighting suit the room. If you have already chosen your tiles and fixtures, we price around them. If not, we guide you. Because tiles, glass and custom vanities have to be ordered, decisions made here set the pace for everything that follows. See our bathroom renovation ideas for inspiration.
-
3
Fixed-price quote and dated schedule
With the scope written down, you receive one fixed-price quote and a dated schedule showing when work starts and when it should finish. Read more about what bathroom renovations cost in Melbourne and what is included in a quote.
-
4
Site preparation and demolition
Before demolition, the route through your home is protected and the room is prepared. Then the old fixtures, tiles, linings and sometimes the floor are removed. This is the noisy, dusty stage, and it is also when any surprises in the walls and floor show themselves. If something unexpected turns up, we stop, show you and agree the next step before continuing.
-
5
Rough-in: plumbing and electrical
With the room stripped back, the licensed plumber and electrician install the hidden services: new pipework and drainage, power points, lighting circuits and fan ducting. Doing this while the walls are open is far cheaper than changing it later, so it is the right moment to confirm exactly where every tap, light and power point will sit.
-
6
Wall and floor preparation
New wall linings go up, any framing changes are made, and the floor is prepared so that it falls gently towards the drain. Getting the falls right matters most in walk-in showers and step-free wet rooms, where there is no hob to contain the water.
-
7
Waterproofing and curing
The waterproofing membrane is applied to the floor and walls of the wet area to the Australian Standard, AS 3740. It then needs time to cure, usually at least a day and longer in cool or damp conditions, before tiling can begin. It is the one stage nobody sees once the job is finished, and the one that matters most to how long the bathroom lasts, so it should never be rushed.
-
8
Tiling and grouting
Wall and floor tiles are set, niches are formed, and the grout and flexible joints are finished. Large-format tiles need flat surfaces and careful setting out, and feature walls take more time because of the cutting and pattern layout. Tiling is often the longest single stage.
-
9
Fit-off: vanity, tapware, glass and lighting
Once the tiling is complete, the vanity, basin, toilet, tapware, mirror and accessories go in, and the electrician fits off the lights and fans. Frameless glass is usually measured after the tiling is finished and then made to size, so we plan for it in the schedule.
-
10
Finishing, cleaning and handover
Painting touch-ups, silicone, a thorough clean and a final check of every fixture come before the handover walkthrough, where we go through the finished room with you before it is signed off.
How long does a bathroom renovation take?
A bathroom renovation can take anywhere from 2 to 3 weeks, depending on how big the renovation is. A compact ensuite with an unchanged layout sits towards the shorter end, and a larger bathroom with layout changes, a wet room floor or custom joinery sits towards the longer end.
Planning, selections and ordering happen before work starts, so the earlier you choose, the earlier your start date. We give you a dated schedule before work begins and manage the trades to keep to it.
How you can help the project run smoothly.
- ◆Choose early. Tiles, tapware, the vanity and glass should be decided before work starts, not during it.
- ◆Plan for no bathroom. Most families stay at home, but the room is out of use for the length of the job, so plan which bathroom everyone will use.
- ◆Clear the way. Move belongings out of the room and the route to it, and let us know about parking and access.
- ◆Ask questions. With one point of contact for the project, you can ask at any stage what is happening next.
Our five-step process summarises how we run each project. You can also see what is included in our services.
Bathroom renovation mistakes to avoid.
Most renovation problems come from a short list of avoidable mistakes. Knowing them makes it much easier to judge a quote and a plan.
- ◆Skimping on waterproofing. Rushing the membrane or the curing time is the most expensive mistake, because the damage shows up behind finished tiles.
- ◆Choosing tiles and fixtures after work starts. Late selections cause delays, rushed decisions and extra cost.
- ◆Forgetting ventilation. A bathroom without effective extraction holds moisture, which leads to mould and peeling paint.
- ◆Planning too little storage and light. Niches, drawers and layered lighting are far cheaper to build in than to add later.
- ◆Hiring on price alone. Check that plumbing and electrical work is done by licensed trades, ask about insurance, and compare quotes on what is included, not only the total.
- ◆Accepting a vague quote. A written scope and a fixed price protect you from surprise extras. See what bathroom renovations cost in Melbourne.
- ◆Underestimating the disruption. The room is out of action while the work is under way (anywhere from 2 to 3 weeks, depending on size), so plan where everyone will wash and when deliveries and trades will be on site.
Renovation process questions, answered.
What is the correct order of work for a bathroom renovation?
Planning and selections come first, then demolition, rough-in plumbing and electrical, wall and floor preparation, waterproofing and curing, tiling, fit-off of fixtures and glass, and finally finishing and handover. Doing the stages in this order avoids rework and protects the waterproofing.
Why does waterproofing need to cure before tiling?
The membrane has to dry and bond properly before it is covered. Tiling too early can trap moisture and compromise the seal. Curing time depends on the product and the conditions, but it is usually at least a day, and tiling does not start until the membrane is ready.
What are the most common bathroom renovation mistakes?
Skimping on waterproofing, choosing tiles and fixtures after work has started, forgetting ventilation, planning too little storage and lighting, hiring on price alone without checking licences and insurance, and accepting a vague quote with no written scope. Our list above explains how to avoid each one.
Do I need to be at home during the renovation?
Not every day. We agree access arrangements with you before work starts, keep you updated as the project moves along, and you have one point of contact to ask what is happening next.
Can I change my mind once the renovation has started?
Small changes are often possible, but late changes to layout, tiles or fixtures can add cost and delay, particularly once waterproofing is complete or items have been ordered. Tell us as early as you can, and we will agree the cost and timing impact with you before going ahead.
How do I live without a bathroom during the renovation?
Most families stay at home and use another bathroom. If the room being renovated is your only bathroom, plan ahead for the length of the project, and we will talk through what is practical for your household at the consultation.
More from our guides.
Bathroom renovation cost in Melbourne
Price bands, what drives the cost and how a fixed-price quote works.
READ THE GUIDEBathroom renovation ideas
Eleven ideas drawn from real Melbourne projects, with photos.
READ THE GUIDELuxury bathroom renovation guide
What makes a bathroom luxury: materials, layouts, lighting and cost.
READ THE GUIDEReady to start your renovation?
Tell us about your project and we will arrange a consultation and site assessment, with a clear scope and a fixed price before any work begins.
Get an Estimate